FDEP NOI: filing for Florida construction stormwater coverage
In Florida, construction disturbing one acre or more, or less within a larger common plan, that discharges to surface waters or an MS4 needs coverage under DEP's Construction Generic Permit. FDEP construction activity page You get it by filing DEP Form 62-621.300(4)(b), the Notice of Intent, with a $400 fee for 5 acres or more or $250 for 1 to 4.99 acres, at least 2 calendar days before construction starts, after your SWPPP is written. FDEP CGP Part 2.1, 2.2, 2.5.1 Checked October 20, 2026.
Sources last checked October 19, 2026. Prepared by our team led by Mohamed Elansary, PhD, with AI research tools. We are not a licensed engineering firm and do not seal plans.
General information; your permit text controls. Not legal advice and not engineering judgment. We make no promise of permit coverage, agency acceptance or compliance.
FDEP NOI at a glance
| Item | Rule | Source |
|---|---|---|
| Permit | NPDES Generic Permit for Stormwater Discharge from Large and Small Construction Activities, DEP Document 62-621.300(4)(a), effective 02/2015 | FDEP CGP permit text |
| Agency | Florida Department of Environmental Protection (DEP) | FDEP construction activity page |
| Before you file | Develop the SWPPP and be ready to implement it | FDEP CGP Part 2.2 |
| Form | DEP Form 62-621.300(4)(b), Notice of Intent to Use Generic Permit for Stormwater Discharge from Large and Small Construction Activities | FDEP CGP Part 2.1.1 |
| Fee | $400 for sites disturbing 5 acres or more; $250 for 1 to 4.99 acres. Sites under 1 acre in a common plan must also apply | FDEP CGP Part 2.1.2 |
| How to file | Online through the DEP Business Portal, paying by check, credit or debit card, or by mail with a check to FDEP, PO Box 3070, Tallahassee, FL 32315 | FDEP CGP Part 2.3 FDEP page |
| Who signs | The responsible authority (for a corporation, a responsible corporate officer), or a duly authorized representative they designate | FDEP CGP Part 2.4, 8.22 |
| Deadline | At least 2 calendar days before clearing, grading, excavating, demolition or other soil disturbance begins | FDEP CGP Part 2.5.1 |
| Coverage | Begins 2 calendar days after DEP finds the NOI complete and lasts 5 years or until you terminate | FDEP CGP Part 2.7.1 |
| After filing | DEP sends an acknowledgment letter. Post the NOI or the letter at the site where the public can see it, and send a copy to the MS4 operator within 7 calendar days if you discharge to an MS4 | FDEP CGP Part 2.6.2-2.6.4 |
| Renewal | Projects running past 5 years file a new NOI and fee at least 2 calendar days before coverage expires | FDEP CGP Part 2.5.2 |
| New operator | Coverage is not transferable. The new operator files its own SWPPP, NOI and fee at least 2 days before taking control; the old operator files an NOT within 14 days | FDEP CGP Part 2.5.3, 7.2 |
| Dewatering | To discharge uncontaminated groundwater, complete Part VI of the NOI and keep site documentation with the SWPPP | FDEP CGP Part 3.4.2-3.4.4 |
| Inspections | At least every 7 calendar days and within 24 hours after a storm of 0.50 inches or more, by a qualified inspector you provide | FDEP CGP Part 6.1, 8.21 |
| Termination | NOT within 14 calendar days after final stabilization, online through the Business Portal or by email to the Notices Center | FDEP CGP Part 7.1, 7.3 |
Filing step by step
- Confirm the site needs coverage: one acre or more disturbed (or part of a common plan) and a discharge to surface waters or an MS4. FDEP page
- Have the SWPPP written and ready to implement. FDEP CGP Part 2.2
- Decide whether you will dewater; if you will discharge groundwater, confirm the site is not a contaminated site and has none within 500 feet (or that DEP has documented remediation), and fill in NOI Part VI. FDEP CGP Part 3.4.2-3.4.3
- Have the responsible authority sign, or a designated representative. FDEP CGP Part 2.4
- File the NOI and fee in the DEP Business Portal, or mail them, at least 2 calendar days before construction. FDEP CGP Part 2.3, 2.5.1
- When the acknowledgment arrives, post it (or the NOI) at the site and send a copy to the MS4 operator within 7 days if you discharge to one. FDEP CGP Part 2.6.3-2.6.4
Proposed rule changes
DEP is proposing amendments to Chapter 62-621, F.A.C., that would update the Construction Generic Permit and its NOI and NOT forms. A public workshop was held November 19, 2025, comments were taken until December 30, 2025, and DEP posted a revised draft rule dated July 22, 2026. FDEP CGP rulemaking drafts page Until DEP adopts a new permit, the 2015 permit and forms above apply. Check the rulemaking page before you file.
What we do
We prepare Florida CGP SWPPPs, written before your NOI as Part 2.2 requires. We prepare the plan document. We do not stamp plans, visit sites or file the NOI; you file it. The site check at checkout applies the Florida limits shown on the Florida hub before payment.
Questions
How much is the FDEP NOI fee?
$400 for construction disturbing 5 acres or more and $250 for 1 to 4.99 acres (CGP Part 2.1.2).
How far ahead do I file the FDEP NOI?
At least 2 calendar days before construction begins. Coverage begins 2 calendar days after DEP finds the NOI complete.
Do I need a SWPPP before filing the NOI in Florida?
Yes. Part 2.2 of the CGP says to develop the SWPPP and be ready to implement it before you submit the NOI.
Where do I file the FDEP NOI?
Online in the DEP Business Portal, or by mail with a check to FDEP, PO Box 3070, Tallahassee, FL 32315.
Can a new contractor use the existing Florida permit coverage?
No. Coverage is not transferable; the new operator files its own SWPPP, NOI and fee at least 2 days before taking control.